“Working design” – Construction of the 110/35/10 kV Soltustik Substation

About project

Construction of the 110/35/10 kV Soltustik Substation, with a capacity of 2 × 25 MVA, and a 110 kV transmission line along the Kyzylorda Highway in Turkistan

Project objective

To improve the reliability of the 110 kV Soltustik Substation and extend the trouble-free service life of its electrical equipment.

Project scope:

  • Construction of the 110 kV Soltustik Substation.

  • Installation of switching equipment at the 110 kV substation, including construction of an equipment access platform.

  • Installation of a floodlight mast.

  • Installation and commissioning of equipment, including new transformers, disconnectors, and suspension insulators at the 110 kV substation.

  • Installation of cables and conductors, followed by acceptance testing.

  • Commissioning works and putting the facility into operation.

 
Scroll to Top