Reconstruction of 220 kV Overhead Transmission Lines at KEGOC JSC’s Aktobe and Western Interregional Electric Networks Branches
- Kazakstan
- 2019 - 22 y.
- KEGOC JSC
About project
Project objective
Modernize the existing power grid to accommodate increased loads from industrial facilities and improve network reliability.
Outcome
Works completed.
Project scope
Reconstruction of overhead transmission lines (OHLs), including the required engineering surveys, preparation and approval of design and cost estimate documentation (including environmental impact assessment documentation), factory acceptance testing, and supply of equipment, materials, and spare parts. The scope also included dismantling, construction, installation, commissioning, and putting the following facilities into operation:
Reconstruction of the 220 kV OHL L-2012 Kempirsay–Orskaya
Reconstruction of the 220 kV OHL L-2022 Kempirsay–Akzhar and L-2092 Akzhar–Aktyubinskaya
Reconstruction of the 220 kV OHL L-2032 Orskaya–Aktyubinskaya
Reconstruction of the 220 kV OHL L-2502 Uralskaya–Stepnaya
Reconstruction of the 220 kV OHL L-2522 Kinel–Uralskaya
Reconstruction of the 220 kV OHL L-2582 Stepnaya–Yuzhnaya
Reconstruction of the 220 kV OHL L-2540 Pravoberezhnaya–Inder