About project
Construction of the 110/35/10 kV Soltustik Substation, with a capacity of 2 × 25 MVA, and a 110 kV transmission line along the Kyzylorda Highway in Turkistan
Project objective
Improve the reliability of the 110 kV Soltustik Substation and extend the trouble-free service life of its electrical equipment.
Project scope
Construction of the 110 kV Soltustik Substation
Installation of switching equipment, including construction of an equipment access platform
Installation of a floodlight mast
Installation and commissioning of new transformers, disconnectors, and suspension insulators
Installation of cables and conductors, followed by acceptance testing
Commissioning and putting the facility into operation